The 2014-2020 Development and Cohesion Fund (FSC 14-20) is the main financial instrument with which policies for economic, social and territorial development and for the removal of economic and social imbalances are implemented. The purpose of the Development and Cohesion Fund is to give programmatic and financial unity to the set of additional interventions to national financing, aimed at rebalancing the economic and social equilibrium between the various areas of the country. The Fund is multi-annual in nature, in line with the articulation over time of the European Union’s Structural Funds programming, guaranteeing the unity and complementarity of the procedures for activating the relative resources with those foreseen for the Community monies.

The intervention of the Fund is intended for financing strategic projects – both infrastructural and intangible – of national, interregional and regional significance, be they major projects or investments divided into individual interventions that are functionally interconnected.

The programme has a budget of 4,080,400,000 euro. RFI participates in the Development and Cohesion Fund with the interventions eligible for funding through CIPE Resolution 54 of 2016 and I - II ADDENDUM - CIPE Resolution 98 of 2017 and CIPE Deliberation 12 of 2018 plus the relative 2017–2021 Programme Contract signed by RFI with the Ministry of Infrastructure and Transport.

In addition, RFI also benefits from resources from the Development Pacts totalling 350,905,307.56 euro for implementing interventions in the regions of Abruzzo, Campania, Molise, Puglia and Sardinia

FSC Operational Plan - RFI Interventions
MIT CODE DESCRIPTION OF THE INTERVENTION ARTICULATION OF THE OPERATIONAL PLAN CIPE DELIBERATION ALLOCATION OF FSC14-20
B1R001 Udine hub (completion) Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 54/2016 1,000,000.00 
B1R002 Rome Metro Line C - Pigneto Interchange Node Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 54/2016 24,000,000.00
B1R003 Fiumetorto Lercara Friddi upgrade - First functional phase Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 54/2016 350,000,000.00
B1R004 Empoli-Siena line - Empoli Granaiolo doubling and electrification Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 54/2016 85,000,000.00
B1R005 Electrification of the Trento-Bassano del Grappa line Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 54/2016 59,000,000.00
B1R006 New Ferrandina-Matera line Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 98/2017 10,000,000.00
B1R007 Caltagirone-Gela Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 98/2017 90,000,000.00
B1R008 Foggia-Cervaro HS station Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 98/2017 20,000,000.00
B1R009 Speeding up the Adriatic - Technological upgrading of Foggia-Bari-Brindisi Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 98/2017 92,000,000.00
B1R010 New Palermo-Catania connection Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 98/2017 866,000,000.00
B1R011 Repair of the Bari junction Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 98/2017 15,000,000.00
B1R012 Doubling and speeding up Frasso Telesino-Vitulano - Lot III San Lorenzo M.-Vitulano Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 98/2017 215,000,000.00
B1R013 Link between the national railway network and Brindisi airport Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 Dec-18 60,000,000.00
B1R014 Doubling Orsara-Bovino Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 98/2017 501,000,000.00
B2R001 Torino Orbassano General Regulatory Plan Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 13,000,000.00
B2R002 Falconara junction Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 1,000,000.00
B2R003 Variant proposed by the Molise Region for the urban and territorial optimisation of the route between km 1+940 (Lot 2 Termoli-Campomarino) and 8+298 Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 150,000,000.00
B2R004 Elimination of level crossings on line SFM2 Torino-Pinerolo Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 5,000,000.00
B2R005 Restoration of the Palermo-Trapani via Milo line Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 34,000,000.00
B2R007 Barletta-Canosa electrification Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 26,000,000.00
B2R008 Burying of the Catania-Siracusa railway line to extend the Catania airport runway Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 235,000,000.00
B2R009 Campoleone-Nettuno railway (Campoleone Aprilia section) Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 15,000,000.00
B2R010 New “Brindisi northbound intermodal” railway junction Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 25,000,000.00
B2R011 Riga variant Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 49,000,000.00
B2R012 San Gavino-Sassari-Olbia Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 74,000,000.00
B2R013 Upgrading the Foligno-Perugia-Terontola line (first phase) Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 32,000,000.00
B2R015 Technological upgrading of the Roma-Napoli via Formia line Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 20,000,000.00
B2R016 Technological adaptation of the Roma‐Napoli via Formia line Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 10,000,000.00
B2R017 Speeding up and elimination of level crossings for the Chivasso-Ivrea-Quincinetto line Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 5,000,000.00
B2R018 B2R039 B2R040 B2R041 Settingiano-Lamezia Terme variant - Technological upgrading interventions for the Settingiano-Lamezia Terme variant - Interventions for underpasses on Settingiano-Lamezia Terme variant - Interventions for eliminating Settingiano-Lamezia Terme variant level crossings - Interventions for civil works Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 307,000,000.00
B2R019 Electrification of Civitanova Macerata Albacina line Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 39,000,000.00
B2R020 Improved accessibility on passageways (subways, paving, platforms, lifts) Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 5,000,000.00
B2R021 Naples Railway Link - Technological adaptation Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 14,000,000.00
B2R022 Complex node at the archaeological site of Pompeii Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 30,600,000.00
B2R023 Complex node at Salerno Centrale railway station Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 25,000,000.00
B2R024 Upgrade to Public Information Systems (IaP) for passageways Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 7,500,000.00
B2R025 Adaptation of the effectiveness of the Roma-Napoli lines via Formia and via Cassino (PC80 gauge) Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 10,000,000.00
B2R026 Upgrade of BcA Benevento-Avellino, Caserta-Benevento and Vairano-Venafro Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 2,500,000.00
B2R027 Computerised Central Apparatus for the Napoli-Salerno line upstream of Vesuvius Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 10,000,000.00
B2R028 Jonica line (electrification): Catanzaro L. - Crotone section - Phase 2 Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 Dec-18 40,000,000.00
B2R032 Removal of the level crossing in Rosora on the Orte-Falconara Marittima railway line Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 98/2017 2,000,000.00
B2R033 Vesuvio Est modal interchange junction Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 98/2017 25,500,000.00
B2R034 Elimination of the level crossing on the Castel Bolognese-Ravenna line in the municipality of Bagnacavallo Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 Dec-18 3,000,000.00
B3R002 Restoration of the Trieste railway junction - Phase 2 works to the Port of Trieste Axis B - B.3 - Action Line 3 - B.3 - Action Line 3 54/2016 17,000,000.00
B3R003 Genoa airport rail link (Erzelli/Airport, Cornigliano Est stops and the General Regulatory Plan for Sestri Ponente) Axis B - B.3 - Action Line 3 - B.3 - Action Line 3 54/2016 800,000.00
C1R001 Completion of the Salerno metro - Arechi Stadium-Pontecagnano Airport section Axis C - C.1 - Action Line 1 - C.1 - Action Line 1 98/2017 100,000,000.00
B1R015 Closure of the Palermo railway link Giachery-Politeama-Notarbartolo section Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 54/2016 100,000,000.00
B2R029 Speeding up of the Tirrenica Sud on the Rosarno variant Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 98/2017 100,000,000.00
B2R035 Electrification and speeding up of Roccaravindola-Isernia-Campobasso - Phase 2 Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 98/2017 50,000,000.00
B2R031 Belluno ring electrification Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 48,000,000.00
B2R030 Padua-Castelfranco line bridge over the Brenta River Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 40,000,000.00
B2R037 Strengthening the Torino-Savona/Fossano-Cuneo/Cuneo-Busca freight connections and logistics area Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 10,000,000.00
B2R036 Elimination of the Turin-Fossano line level crossings Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 54/2016 4,800,000.00
B2R038 Variant on the new location for the elimination of level crossings in the municipality of Villanova sull’Arda Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 Dec-18 3,000,000.00
B1R016 Securing the Cuneo-Ventimiglia line Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 54/2016 1,500,000.00
B3R005 Energy and Equipment General Regulatory Plan for the Vandoies station on the Fortezza-San Candido line Axis B - B.3 - Action Line 3 - B.3 - Action Line 3 Dec-18 1,500,000.00
B3R004 Connection of the Borgata Quaglia-Le Gru stop to Borgata Lesna Axis B - B.3 - Action Line 3 - B.3 - Action Line 3 54/2016 700,000.00
TOTAL 4,080,400,000.00