The 2014-2020 Development and Cohesion Fund (FSC 14-20) is the main financial instrument with which policies for economic, social and territorial development and for the removal of economic and social imbalances are implemented. The purpose of the Development and Cohesion Fund is to give programmatic and financial unity to the set of additional interventions to national financing, aimed at rebalancing the economic and social equilibrium between the various areas of the country. The Fund is multi-annual in nature, in line with the articulation over time of the European Union’s Structural Funds programming, guaranteeing the unity and complementarity of the procedures for activating the relative resources with those foreseen for the Community monies.
The intervention of the Fund is intended for financing strategic projects – both infrastructural and intangible – of national, interregional and regional significance, be they major projects or investments divided into individual interventions that are functionally interconnected.
The programme has a budget of 4,080,400,000 euro. RFI participates in the Development and Cohesion Fund with the interventions eligible for funding through CIPE Resolution 54 of 2016 and I - II ADDENDUM - CIPE Resolution 98 of 2017 and CIPE Deliberation 12 of 2018 plus the relative 2017–2021 Programme Contract signed by RFI with the Ministry of Infrastructure and Transport.
In addition, RFI also benefits from resources from the Development Pacts totalling 350,905,307.56 euro for implementing interventions in the regions of Abruzzo, Campania, Molise, Puglia and Sardinia
FSC Operational Plan - RFI Interventions | ||||
---|---|---|---|---|
MIT CODE | DESCRIPTION OF THE INTERVENTION | ARTICULATION OF THE OPERATIONAL PLAN | CIPE DELIBERATION | ALLOCATION OF FSC14-20 |
B1R001 | Udine hub (completion) | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 54/2016 | 1,000,000.00 |
B1R002 | Rome Metro Line C - Pigneto Interchange Node | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 54/2016 | 24,000,000.00 |
B1R003 | Fiumetorto Lercara Friddi upgrade - First functional phase | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 54/2016 | 350,000,000.00 |
B1R004 | Empoli-Siena line - Empoli Granaiolo doubling and electrification | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 54/2016 | 85,000,000.00 |
B1R005 | Electrification of the Trento-Bassano del Grappa line | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 54/2016 | 59,000,000.00 |
B1R006 | New Ferrandina-Matera line | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 98/2017 | 10,000,000.00 |
B1R007 | Caltagirone-Gela | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 98/2017 | 90,000,000.00 |
B1R008 | Foggia-Cervaro HS station | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 98/2017 | 20,000,000.00 |
B1R009 | Speeding up the Adriatic - Technological upgrading of Foggia-Bari-Brindisi | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 98/2017 | 92,000,000.00 |
B1R010 | New Palermo-Catania connection | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 98/2017 | 866,000,000.00 |
B1R011 | Repair of the Bari junction | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 98/2017 | 15,000,000.00 |
B1R012 | Doubling and speeding up Frasso Telesino-Vitulano - Lot III San Lorenzo M.-Vitulano | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 98/2017 | 215,000,000.00 |
B1R013 | Link between the national railway network and Brindisi airport | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | Dec-18 | 60,000,000.00 |
B1R014 | Doubling Orsara-Bovino | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 98/2017 | 501,000,000.00 |
B2R001 | Torino Orbassano General Regulatory Plan | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 13,000,000.00 |
B2R002 | Falconara junction | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 1,000,000.00 |
B2R003 | Variant proposed by the Molise Region for the urban and territorial optimisation of the route between km 1+940 (Lot 2 Termoli-Campomarino) and 8+298 | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 150,000,000.00 |
B2R004 | Elimination of level crossings on line SFM2 Torino-Pinerolo | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 5,000,000.00 |
B2R005 | Restoration of the Palermo-Trapani via Milo line | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 34,000,000.00 |
B2R007 | Barletta-Canosa electrification | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 26,000,000.00 |
B2R008 | Burying of the Catania-Siracusa railway line to extend the Catania airport runway | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 235,000,000.00 |
B2R009 | Campoleone-Nettuno railway (Campoleone Aprilia section) | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 15,000,000.00 |
B2R010 | New “Brindisi northbound intermodal” railway junction | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 25,000,000.00 |
B2R011 | Riga variant | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 49,000,000.00 |
B2R012 | San Gavino-Sassari-Olbia | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 74,000,000.00 |
B2R013 | Upgrading the Foligno-Perugia-Terontola line (first phase) | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 32,000,000.00 |
B2R015 | Technological upgrading of the Roma-Napoli via Formia line | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 20,000,000.00 |
B2R016 | Technological adaptation of the Roma‐Napoli via Formia line | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 10,000,000.00 |
B2R017 | Speeding up and elimination of level crossings for the Chivasso-Ivrea-Quincinetto line | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 5,000,000.00 |
B2R018 B2R039 B2R040 B2R041 | Settingiano-Lamezia Terme variant - Technological upgrading interventions for the Settingiano-Lamezia Terme variant - Interventions for underpasses on Settingiano-Lamezia Terme variant - Interventions for eliminating Settingiano-Lamezia Terme variant level crossings - Interventions for civil works | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 307,000,000.00 |
B2R019 | Electrification of Civitanova Macerata Albacina line | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 39,000,000.00 |
B2R020 | Improved accessibility on passageways (subways, paving, platforms, lifts) | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 5,000,000.00 |
B2R021 | Naples Railway Link - Technological adaptation | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 14,000,000.00 |
B2R022 | Complex node at the archaeological site of Pompeii | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 30,600,000.00 |
B2R023 | Complex node at Salerno Centrale railway station | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 25,000,000.00 |
B2R024 | Upgrade to Public Information Systems (IaP) for passageways | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 7,500,000.00 |
B2R025 | Adaptation of the effectiveness of the Roma-Napoli lines via Formia and via Cassino (PC80 gauge) | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 10,000,000.00 |
B2R026 | Upgrade of BcA Benevento-Avellino, Caserta-Benevento and Vairano-Venafro | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 2,500,000.00 |
B2R027 | Computerised Central Apparatus for the Napoli-Salerno line upstream of Vesuvius | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 10,000,000.00 |
B2R028 | Jonica line (electrification): Catanzaro L. - Crotone section - Phase 2 | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | Dec-18 | 40,000,000.00 |
B2R032 | Removal of the level crossing in Rosora on the Orte-Falconara Marittima railway line | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 98/2017 | 2,000,000.00 |
B2R033 | Vesuvio Est modal interchange junction | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 98/2017 | 25,500,000.00 |
B2R034 | Elimination of the level crossing on the Castel Bolognese-Ravenna line in the municipality of Bagnacavallo | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | Dec-18 | 3,000,000.00 |
B3R002 | Restoration of the Trieste railway junction - Phase 2 works to the Port of Trieste | Axis B - B.3 - Action Line 3 - B.3 - Action Line 3 | 54/2016 | 17,000,000.00 |
B3R003 | Genoa airport rail link (Erzelli/Airport, Cornigliano Est stops and the General Regulatory Plan for Sestri Ponente) | Axis B - B.3 - Action Line 3 - B.3 - Action Line 3 | 54/2016 | 800,000.00 |
C1R001 | Completion of the Salerno metro - Arechi Stadium-Pontecagnano Airport section | Axis C - C.1 - Action Line 1 - C.1 - Action Line 1 | 98/2017 | 100,000,000.00 |
B1R015 | Closure of the Palermo railway link Giachery-Politeama-Notarbartolo section | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 54/2016 | 100,000,000.00 |
B2R029 | Speeding up of the Tirrenica Sud on the Rosarno variant | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 98/2017 | 100,000,000.00 |
B2R035 | Electrification and speeding up of Roccaravindola-Isernia-Campobasso - Phase 2 | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 98/2017 | 50,000,000.00 |
B2R031 | Belluno ring electrification | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 48,000,000.00 |
B2R030 | Padua-Castelfranco line bridge over the Brenta River | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 40,000,000.00 |
B2R037 | Strengthening the Torino-Savona/Fossano-Cuneo/Cuneo-Busca freight connections and logistics area | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 10,000,000.00 |
B2R036 | Elimination of the Turin-Fossano line level crossings | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | 54/2016 | 4,800,000.00 |
B2R038 | Variant on the new location for the elimination of level crossings in the municipality of Villanova sull’Arda | Axis B - B.2 - Action Line 2 - B.2 - Action Line 2 | Dec-18 | 3,000,000.00 |
B1R016 | Securing the Cuneo-Ventimiglia line | Axis B - B.1 - Action Line 1 - B.1 - Action Line 1 | 54/2016 | 1,500,000.00 |
B3R005 | Energy and Equipment General Regulatory Plan for the Vandoies station on the Fortezza-San Candido line | Axis B - B.3 - Action Line 3 - B.3 - Action Line 3 | Dec-18 | 1,500,000.00 |
B3R004 | Connection of the Borgata Quaglia-Le Gru stop to Borgata Lesna | Axis B - B.3 - Action Line 3 - B.3 - Action Line 3 | 54/2016 | 700,000.00 |
TOTAL | 4,080,400,000.00 |