This section contains the Network Statement of the Piedmontose Regional Railway Infrastructure (PRRI) and any further documents and communications to stakeholders relevant to the regional infrastructure, of which RFI S.p.A. is the Infrastructure Manager, pursuant to the Deed of Concession (Managerial Resolution no. 2912/A1800A/2023 of the Piedmont Region), following the takeover from the previous concessionaire.

In accordance with art. 14 of Legislative Decree 112/2015, RFI has published the first draft of “Network Statement 2026 of the Piedmontese Regional Railway Infrastructure", for the purpose of starting the consultation phase with the RUs, Regions, Autonomous Provinces and other interested parties.

Any comments by the interested parties must be received no later than 31 July 2024 to the following e-mail: rfi-ad.ara@pec.rfi.it.

documents download 

By CEO Provision No. 5 of 23 April 2024, the Managing Director of RFI issued the 2025 Network Statement of the Piedmontese Regional Railway Infrastructure – April 2024 II edition.

In the NS, the National Railway Infrastructure Manager sets out:

  • the rules and procedures governing the requirements for requesting capacity and those relating to the process of allocating capacity, which are valid from 8 March 2024 as regards the service timetable applicable from 15 December 2024 to 13 December 2025;
  • the rules and information applicable to the working timetable in force from 15 December 2024 to 13 December 2025, such as the rules governing the obligations and responsibilities of RFI and RUs/Requesters with regard to the signing and execution of the transactions.

documents download 

The 2024 Piedmontese Regional Railway Infrastructure Network Statement – June 2023 edition, relating to the service timetable in force from 10 December 2023 to 14 December 2024, elaborated by the previous Infrastructure Manager GTT S.p.A, is available.

In the NS, the Railway Infrastructure Manager sets out:

  • the rules and procedures governing the requirements for requesting capacity and those relating to the process of allocating capacity, which are valid from 10 March 2023 as regards the service timetable applicable from 10 December 2023 to 14 December 2024,
  • the rules and information applicable to the working timetable in force from 10 December 2023 to 14 December 2024, such as the rules governing the obligations and responsibilities of RFI and RUs/Requesters with regard to the signing and execution of the transactions.

documents download